One megawatt-hour,
start to finish.

Numbers make a proposal credible. This example shows how a 1 MWh C&I system is justified, with every assumption visible so you can substitute your own.

Key points

Step 1: read the load profile

The factory in this example has a 320 kW summer peak lasting roughly three hours, driven by air compression and refrigeration. Half-hourly meter data over twelve months shows a consistent evening peak and a demand charge that dominates the bill. The design target is to clip 200 kW for three hours, not to eliminate the peak entirely — partial clipping usually gives the best return per invested capital.

The details

Step 2: configure the cabinets

200 kW for three hours is 600 kWh usable. At 90% depth of discharge that means roughly 670 kWh installed. Two 125 kW / 418 kWh cabinets give 836 kWh installed and 250 kW of power, leaving headroom for peak growth and degradation over the system life. Parallel cabinets also allow one unit to be serviced without a full site shutdown.

The details

Step 3: installation reality

The site had 4 metres of clear access, a 400 V busbar and no roof shading. Cabinets were placed on a concrete pad with a service corridor and a defined separation from the building. Cable runs were kept short to limit losses. The electrical designer confirmed earthing, protection coordination and the export limiter before ordering — each of these is a common source of delay if left until commissioning.

The details

Step 4: payback with assumptions shown

Assume 200 kW clipped for 600 hours per year, a demand charge saving of 90 USD per kW-year and a time-of-use spread of 0.06 USD per kWh on 300 MWh shifted annually. That is 18,000 USD in demand savings plus 18,000 USD in energy spread, roughly 36,000 USD per year before degradation. Against an installed system cost in the range of 120,000 to 160,000 USD, simple payback is about 3.5 to 4.5 years. Replace these numbers with your own tariff and load data before making a decision — the method is what transfers, not the figures.

Frequently asked questions

  • Why not size to eliminate the entire peak?

    The last portion of a peak is expensive to clip relative to the savings. Partial clipping normally delivers a better return per unit of capital.

  • How does degradation affect payback?

    A quality LFP system is typically warranted to retain a high percentage of capacity after ten years. Model a modest annual decline in your cash-flow calculation to stay conservative.

  • Can cabinets be expanded later?

    Yes — modular cabinets parallel on site. Design the busbar, cable runs and physical space for a second phase from the start.